Document control record
Document prepared by:
Unit 1608,
16/F, Tower B, Manulife Financial Centre,
223 – 231 Wai
Yip Street, Kwun Tong, Kowloon
Hong Kong S.
A. R.
|
T |
+852 3664 6888 |
A person using
a)
Using
the documents or data in electronic form without requesting and checking them
for accuracy against the original hard copy version.
b)
Using
the documents or data for any purpose not agreed to in writing by
|
Document control |
||||||
|
Report title |
2nd Monthly EM&A Report |
|||||
|
Document ID |
MMR |
Project number |
P520574 |
|||
|
File path |
520574-0000-PLN-NM-0004 [0] |
|||||
|
Client |
|
|||||
|
Client contact |
|
Client reference |
|
|||
|
Rev |
Date |
Revision details/status |
Author |
Reviewer |
Verifier |
Approver |
|
0 |
|
Submitted to IEC |
Various |
K.Chau |
|
FL |
|
1 |
|
Submitted to IEC |
Various |
K.Chau |
|
FL |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Current revision |
|
|||||
|
Approval |
|||
|
Reviewer’s
signature |
|
Approver’s
signature |
|
|
Name |
Keith Chau |
Name |
Fredrick
Leong |
|
Title |
Principal
Consultant, Environmental |
Title |
Executive
Director, Environment & Planning - Greater China |


Contents
3 Environmental Monitoring Requirements
4 Implementation Status on Environmental Mitigation
Measures
6 Environmental Site Inspection
7 Environmental Non-conformance
9 Review of EM&A Data and EIA Predictions
Appendix
|
Construction Programme |
|
|
Project Organization Chart and Contact Details |
|
|
Monitoring Programme for Reporting Period
|
|
|
Calibration Certificates |
|
|
Event and Action Plan |
|
|
Implementation Status of Mitigation Measures |
|
|
Monitoring Results with Graphical Presentations |
|
|
Waste Flow Table |
|
|
Joint site inspection record for Reporting Period |
|
|
Monitoring Schedule for the Next Month |
Aurecon Hong Kong Limited (Aurecon) was
commissioned by the Yau Lee Construction Co, Ltd (Yau Lee) to undertake the
role of Environmental Team (ET) for carrying out the environmental monitoring
and audit (EM&A) works for the “Contract No. SS
H504 Design and Construction of Chai Wan Government Complex and Vehicle Depot
(The Project).
An
Environmental Permit (EP) No. EP-505/2015 was issued by the Environmental
Protection Department (EPD) on 17 December 2015 for the construction of this
project based on the Environmental Impact Assessment (EIA) Report (Register No:
AEIAR-191/2015) approved by the EPD. The latest EP No. EP-505/2015/A was
subsequently issued by the EPD on 8 November 2019 based on the documents
(including an Environmental Review Report (ERR)) for the application of
Variation of Environmental Permit.
The construction phase and EM&A
programme of the Project commenced on 25 November 2021.
This
2nd Monthly EM&A Report presents the EM&A works conducted
from 1 December 2021 to 31 December 2021 in accordance with the EM&A Manual.
Summary of
Construction Works undertaken during Report Period
The
major construction works undertaken during the reporting period include:
|
-
Pre-drilling work to boreholes |
|
-
Piling work |
Environmental
Monitoring and Audit Progress
A
summary of the monitoring activities in this reporting period is listed below:
|
-
Construction Noise Monitoring
during normal weekdays at each monitoring station |
4 times |
|
-
Joint Environmental Site
Inspection |
5 times |
Nosie
4
sets of 30-minute construction noise measurement were carried out at each
monitoring stations during normal weekdays f the reporting period. No
exceedance of Action and Limit Levels of construction noise was recorded during
the reporting period.
Environmental Site Inspection
A
joint environmental site inspection was carried out by the Engineer's Representative,
the representatives of the Contractor, the IEC and the ET on 03,10,16,23 and 30
December 2021. The Contractor has generally implemented the mitigation measures
as recommended.
Environmental
Exceedance/Non-conformance/Compliant/Summons and Prosecution
No
exceedance of the Action and Limit Levels of construction noise was recorded at
designated monitoring stations during the reporting period.
No
non-compliance event was recorded during the reporting period.
No
environmental complaint and summons/prosecutions was received in this reporting
period.
EPD
conducted general site inspection on 15 December 2021. No special findings were
identified during the inspection.
Future Key Issues
Works
to be undertaken in the next month include:
|
-
Tree protection works |
|
-
Pre-drilling works. (Zone A
& Zone B) |
|
-
Piling works. (Zone A) |
|
-
Sheet pile installation. |
|
-
ELS works. |
|
-
Off-site mock up construction. |
Potential
environmental impacts arising from the above construction activities are mainly
associated with dust, construction noise, site runoff and waste management.

|
Construction Activities
Undertaken |
|
-
Pre-drilling work to borehole. |
|
-
Pilling work. |
|
Permit / Licenses /
Notifiation |
Reference |
Validity Period |
Remark |
|
Environmental Permit (EP) |
EP-505/2015/A |
Throughout the Contract |
Permit granted on 8 November 2019 |
|
Notification of Construction Works as required under Air Pollution
Control (Construction Dust) Regulation |
469716 |
Throughout the Contract |
Approved on 21 July 2021 |
|
Registration of Waste Producer under Waste Disposal Ordinance |
7041313 |
Throughout the Contract |
Approved on 13 August 2021 |
|
Registration as Chemical Waste Producer |
5213-163-Y2782-01 |
Throughout the Contract |
Approved on 24 August 2021 |
|
Construction Noise Permit |
GW-RS0759-21 |
14 April 2022 |
Approved on 4 October 2021 |
|
Effluent Discharge License under Water Pollution Control Ordinance |
WT00038924-2021 |
30 September 2026 |
Approved on 9 December 2021 |
|
Proposed Noise Monitoring Location |
Remark |
|
|
NM1 |
Ground Floor at Heng Fa Chuen Block 50 |
- |
|
NM2a |
Lamp Post no. 47447 at Sheung Mau Street |
* |
|
NM3 |
Rooftop of THEi Campus |
- |
|
Remark: * - |
Hong Kong Institute of
Vocational Education (Chai Wan) - Academic Block (NM2) is the noise
monitoring stations for the construction phase EM&A programme as
identified in the approved EM&A Manual for the Project. The access to NM2
and Knight Court (as a VTC Senior Quarters and NSR3 in approved EIA) were
denied. A search for alternative noise
monitoring locations along Shing Tai Road and Sheung Mau Street was carried
out during the site visit on 4 October 2021. Lamp Post no. 47447 at Sheung
Mau Street (NM2a), which is located between project site and original noise
monitoring location, Hong Kong Institute of Vocational Education (Chai Wan) -
Academic Block (NM2), is found suitable and available to be an alternative
noise monitoring location for NM2. Also, NM2a, which has a direct line of
sight towards project site (where construction works will be carried out and
likely to have noise impacts), is located closer to project site than NM2 and
thus considered as a representative noise monitoring location. Monitoring
position at NM2a is proposed at 2m above ground due to security concerns and
minimize the road traffic noise contribution. Noise measurement at NM2a will
be considered as free-field and a correction of +3dB(A) would be made to the
noise monitoring results. The
alternative location of NM2a, were therefore proposed and agreed by the Independent
Environmental Checker (IEC). |
|

|
Time Period |
Parameters |
|
Daytime on normal weekdays (0700-1900 hrs) |
Leq(30 mins), L10(5 mins) and L90(5 mins) |
|
Evening time on all days (1900-2300 hrs) and Holidays
(including Sundays) during daytime and evening (0700-2300 hrs) |
Leq(5 mins), L10(5 mins) and L90(5 mins) |
|
All days during the night-time (2300-0700 hrs of the next day) |
Leq(5 mins) L10(5 mins) and L90(5 mins) |
|
Monitoring Station |
Monitoring Equipment
(Sound Level Meter and Calibrator) |
|
NM1 |
Sound Level Meter: Rion NL
52(s/n:00643040) and (s/n:01010406) Calibrator: Larson Davis Cal
200(s/n: 16878) |
|
NM2a |
|
| NM3 |
|
Monitoring Station |
Action Level |
Limit Level |
|
|
Noise Criteria, Leq(30mins), dB(A) |
Remark |
||
|
NM1 |
When one documented complaint is received |
75 |
Applicable during 0700 – 1900 hours, Monday to Saturday |
|
NM2a |
70 65 (during examination) |
||
| NM3 |
70 65 (during examination) |
||
• NM1: Road traffic noise and railway
noise.
• NM2a: Road traffic noise and Yau Lee
Site.
• NM3: Road Traffic Noise. Minor
noise from Cargo Handling Area.
03 December 2021
• Oil
stain was observed on the ground near mobile crane. The contractor was reminded
to clean the oil stain and dispose of as chemical waste.
10
December 2021
• Several
chemical storage drums without labels and drip pans have been found. Contractor was reminded to
provide labels and drip pans for chemical drums properly.
• Oil stain was observed near the GI works area. The
contractor was reminded to clean the oil stain and dispose of as chemical
waste.
16
December 2021
• Oil stain was observed under the
mobile crane. The contractor was reminded to clean the oil stain and dispose of
as chemical waste.
• Drip tray was observed full. The
contractor was reminded to remove the oil inside drip tray regularly and
dispose of as chemical waste.
23 December 2021
• Oil stain was observed. The contractor was reminded to
clean the oil stain and dispose of as chemical waste.
• The drip tray is full and oil is dripping from the drip
tray. Drip tray should be sealed to prevent oil leakage. Drip tray should be
sealed and cleared regularly to prevent oil dripping out from the drip tray.
30 December 2021
• Dry haul road is observed. Regular water spraying shall
be implemented on dry haul road for dust suppression.
• The drip tray is full. The Contractor shall clear the
oil inside the drip tray regularly.
• Chemical containers are observed without drip tray and
without proper labels. Suitable drip trays shall be provided for the storage of
chemical containers.
• Oil stain is observed under the air compressor. The oil
under the air compressor shall be cleaned and dispose of as chemical waste.
- Tree
protection works
- Pre-drilling works for pilling works. (Zone A & Zone B)
- Piling works. (Zone A)
- Sheet pile installation.
- ELS work.
- Off site mock up construction.
|
Monitoring Station |
EIA Predicted Construction Noise Levels, dB(A) |
Baseline Noise Levels, dB(A) |
Noise Monitoring Results, dB(A) |
|
|
|
Leq(30mins),
Average |
Range |
||
|
NM1 |
62 |
65.1 |
64.0 |
63-65 |
|
NM2a |
69 |
73.4 |
73.8* |
73-74
(65-73*) |
|
NM3 |
66 |
69.8 |
67.3 |
66-68 |
Note: *The measured noise
levels exceeded the noise level of 70dB(A) and they were higher than the
baseline level of 73.4 dB(A) for NM2a. Therefore,
baseline corrections were carried out and the corrected noise levels which
solely represent the noise levels of Construction works are lower than the
noise criteria. As such the EAP was not triggered.
Prepared by:
Aurecon Hong Kong Limited
Unit 1608, 16/F, Tower B, Manulife Financial Centre,
223 – 231 Wai Yip Street, Kwun Tong,
Kowloon Hong Kong S. A. R.
T: +852 3664 6888
F: +852 3664 6999