Document control record
Document prepared by:
Unit 1608, 16/F, Tower B, Manulife Financial Centre,
223 – 231 Wai Yip Street, Kwun Tong, Kowloon
Hong Kong S. A. R.
|
T |
+852 3664 6888 |
A person using
a)
Using
the documents or data in electronic form without requesting and checking them
for accuracy against the original hard copy version.
b)
Using
the documents or data for any purpose not agreed to in writing by
|
Document control |
||||||
|
Report title |
Third Monthly EM&A Report |
|||||
|
Document ID |
MMR |
Project number |
P520574 |
|||
|
File path |
520574-0000-PLN-NM-0005 [0] |
|||||
|
Client |
|
|||||
|
Client contact |
|
Client reference |
|
|||
|
Rev |
Date |
Revision details/status |
Author |
Reviewer |
Verifier |
Approver |
|
0 |
|
Submitted to IEC |
Various |
K.Chau |
|
FL |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Current revision |
|
|||||
|
Approval |
|||
|
Reviewer’s
signature |
|
Approver’s
signature |
|
|
Name |
Keith Chau |
Name |
Fredrick Leong |
|
Title |
Principal
Consultant, Environmental |
Title |
Executive
Director, Environment & Planning - Greater China |


Contents
3 Environmental Monitoring Requirements
4 Implementation Status on Environmental Mitigation
Measures
6 Environmental Site Inspection
7 Environmental Non-conformance
9 Review of EM&A Data and EIA Predictions
Appendix
|
Construction Programme |
|
|
Project Organization Chart and Contact Details |
|
|
Monitoring
Programme for Reporting Period |
|
|
Calibration Certificates |
|
|
Event and Action Plan |
|
|
Implementation Status of Mitigation Measures |
|
|
Monitoring Results with Graphical Presentations |
|
|
Waste Flow Table |
|
|
Joint site inspection record for Reporting Period |
|
|
Monitoring Schedule for the Next Month |
Aurecon Hong Kong Limited (Aurecon) was commissioned by the Yau Lee Construction Co, Ltd (Yau Lee) to undertake the role of Environmental Team (ET) for carrying out the environmental monitoring and audit (EM&A) works for the “Contract No. SS H504 Design and Construction of Chai Wan Government Complex and Vehicle Depot (The Project).
An Environmental Permit (EP) No. EP-505/2015 was issued by the Environmental Protection Department (EPD) on 17 December 2015 for the construction of this project based on the Environmental Impact Assessment (EIA) Report (Register No: AEIAR-191/2015) approved by the EPD. The latest EP No. EP-505/2015/A was subsequently issued by the EPD on 8 November 2019 based on the documents (including an Environmental Review Report (ERR)) for the application of Variation of Environmental Permit.
The construction phase and EM&A programme of the Project commenced on 25 November 2021.
This 3rd Monthly EM&A Report presents the EM&A works conducted from 1 January 2022 to 31 January 2022 in accordance with the EM&A Manual.
Summary of Construction Works undertaken during Report Period
The major construction works undertaken during the reporting period include:
|
-
Pre-drilling work to boreholes |
|
-
Piling work |
Environmental Monitoring and Audit Progress
A summary of the monitoring activities in this reporting period is listed below:
|
-
Construction Noise Monitoring
during normal weekdays at each monitoring station |
4 times |
|
-
Joint Environmental Site
Inspection |
4 times |
Nosie
4 sets of 30-minute construction noise measurement were carried out at each monitoring stations during normal weekdays of the reporting period. No exceedance of Action and Limit Levels of construction noise was recorded during the reporting period.
Environmental
Site Inspection
A joint environmental site inspection was carried out by the Engineer's Representative, the representatives of the Contractor, the IEC and the ET on 07,12,20 and 27 January 2022. The Contractor has generally implemented the mitigation measures as recommended.
Environmental
Exceedance/Non-conformance/Compliant/Summons and Prosecution
No exceedance of the Action and Limit Levels of construction noise was recorded at designated monitoring stations during the reporting period.
No non-compliance event was recorded during the reporting period.
No environmental complaint and summons/prosecutions was received in this reporting period.
EPD conducted general site inspection on 17 January 2022. No special findings were identified during the inspection.
Future
Key Issues
Works to be undertaken in the next month include:
|
-
Tree protection works |
|
-
Pre-drilling works. (Zone A
& Zone B) |
|
-
Piling works. (Zone A) |
|
-
Sheet pile installation. |
|
-
ELS works. |
|
-
Off-site mock up construction. |
Potential environmental impacts arising from the above construction activities are mainly associated with dust, construction noise, site runoff and waste management.

|
Construction Activities Undertaken |
|
-
Pre-drilling work to borehole. |
|
-
Pilling work. |
|
Permit / Licenses / Notifiation |
Reference |
Validity Period |
Remark |
|
Environmental Permit (EP) |
EP-505/2015/A |
Throughout the Contract |
Permit granted on 8 November 2019 |
|
Notification of Construction Works as required under Air Pollution
Control (Construction Dust) Regulation |
469716 |
Throughout the Contract |
Approved on 21 July 2021 |
|
Registration of Waste Producer under Waste Disposal Ordinance |
7041313 |
Throughout the Contract |
Approved on 13 August 2021 |
|
Registration as Chemical Waste Producer |
5213-163-Y2782-01 |
Throughout the Contract |
Approved on 24 August 2021 |
|
Construction Noise Permit |
GW-RS0759-21 |
14 April 2022 |
Approved on 4 October 2021 |
|
Effluent Discharge License under Water Pollution Control Ordinance |
WT00038924-2021 |
30 September 2026 |
Approved on 9 December 2021 |
|
Proposed Noise Monitoring Location |
Remark |
|
|
NM1 |
Ground Floor at Heng Fa Chuen Block 50 |
- |
|
NM2a |
Lamp Post no. 47447 at Sheung Mau Street |
* |
|
NM3 |
Rooftop of THEi Campus |
- |
|
Remark: * - |
Hong Kong Institute of
Vocational Education (Chai Wan) - Academic Block (NM2) is the noise
monitoring stations for the construction phase EM&A programme as
identified in the approved EM&A Manual for the Project. The access to NM2
and Knight Court (as a VTC Senior Quarters and NSR3 in approved EIA) were
denied. A search for alternative
noise monitoring locations along Shing Tai Road and Sheung Mau Street was
carried out during the site visit on 4 October 2021. Lamp Post no. 47447 at Sheung
Mau Street (NM2a), which is located between project site and original noise
monitoring location, Hong Kong Institute of Vocational Education (Chai Wan) -
Academic Block (NM2), is found suitable and available to be an alternative
noise monitoring location for NM2. Also, NM2a, which has a direct line of
sight towards project site (where construction works will be carried out and
likely to have noise impacts), is located closer to project site than NM2 and
thus considered as a representative noise monitoring location. Monitoring
position at NM2a is proposed at 2m above ground due to security concerns and
minimize the road traffic noise contribution. Noise measurement at NM2a will
be considered as free-field and a correction of +3dB(A) would be made to the
noise monitoring results. The
alternative location of NM2a, were therefore proposed and agreed by the
Independent Environmental Checker (IEC). Due to the adjustment of the
location of AM2 to AM2a, the measured noise levels at AM2a would represent
the noise levels at AM2. |
|
![]()

|
Time Period |
Parameters |
|
Daytime on normal weekdays (0700-1900 hrs) |
Leq(30 mins), L10(5 mins) and L90(5 mins) |
|
Evening time on all days (1900-2300 hrs) and Holidays
(including Sundays) during daytime and evening (0700-2300 hrs) |
Leq(5 mins), L10(5 mins) and L90(5 mins) |
|
All days during the night-time (2300-0700 hrs of the next day) |
Leq(5 mins) L10(5 mins) and L90(5 mins) |
|
Monitoring Station |
Monitoring Equipment (Sound Level Meter and Calibrator) |
|
NM1 |
Sound Level Meter: Rion NL
52(s/n:00643040) and (s/n:01010406) Calibrator: Larson Davis Cal
200(s/n: 16878) |
|
NM2a |
|
| NM3 |
|
Monitoring Station |
Action Level |
Limit Level |
|
|
Nosfff Noise Criteria,Leq(30mins), dB(A) |
Remark |
||
|
NM1 |
When one documented complaint is received |
75 |
Applicable during 0700 – 1900 hours, Monday to Saturday |
|
NM2a |
70 65 (during examination) |
||
| NM3 |
70 65 (during examination) |
||
• NM1: Road traffic noise and railway noise.
• NM2a: Road traffic noise and Yau Lee Site.
• NM3: Road Traffic Noise. Minor noise from Cargo Handling Area.
·
When Measured noise level (Leq 30mins) > Baseline noise level
(Leq30), Construction noise level is calculated
·
Construction noise level = Measured noise level (Leq 30 mins) – Baseline
noise level
·
If Measured noise level (Leq 30mins) < Baseline noise level,
Corrected noise level = Measured noise level
07 January 2022
• Oil stain was observed under the pre-drilling rig. The contractor was remained to clear Oil stains and dispose of as chemical waste.
• Dusty haul road was observed. The contractor shall improve the haul road dust water spraying for dust suppression.
• The excavated slurry was observed dripping at the back of the truck. The contractor was remained to provide appropriate measures to the trucks in order to prevent adverse environmental impacts to the public road.
12
January 2022
• The
drip tray was full. The drip tray shall be cleared regularly to maintain its
proper function.
• Oil drums were observed without drip trays. Oil drums shall be placed on drip trays.
20
January 2022
• Sandbag
barriers were not provided for temporary stockpiling area. Sandbags and
channels shall be provided to divert the washout of temporary stockpile to silt
removal facilities.
27 January 2022
• Oil stain was observed. The oil stain shall be cleared and disposed of as chemical waste.
• General wastes were found in non-inert waste storage tank. General waste shall be stored properly to enhance reuse or recycling of material and disposal of it.
• Chemical container was observed without drip tray. It shall be placed on a drip tray.
• Cement bags were not covered entirely by impervious sheeting. They shall be covered entirely by impervious sheeting.
- Tree
protection works
- Pre-drilling works for pilling works. (Zone A & Zone B)
- Piling works. (Zone A)
- Sheet pile installation.
- ELS work.
- Off site mock up construction.
|
Monitoring Station |
EIA Predicted Construction Noise Levels, dB(A) |
Baseline Noise Levels, dB(A) |
Noise Monitoring Results, dB(A) |
|
|
|
Leq(30mins),
Average |
Range |
||
|
NM1 |
62 |
65.1 |
64.0 |
63-65 |
|
NM2a |
69 |
73.4 |
74.0
(67.5*) |
73-75
(62-69*) |
|
NM3 |
66 |
69.8 |
68.0 |
66-68 |
Note: *The measured noise
levels exceeded the noise level of 70dB(A) and they were higher than the
baseline level of 73.4 dB(A) for NM2a.
Therefore, baseline corrections were carried out and the corrected noise
levels which solely represent the noise levels of Construction works are lower
than the noise criteria. As such the EAP was not triggered. Details are mentioned in Section 5.1.3 and
summarised in Appendix 7.
Prepared by:
Aurecon Hong Kong Limited
Unit 1608, 16/F, Tower B, Manulife Financial Centre,
223 – 231 Wai Yip Street, Kwun Tong,
Kowloon Hong Kong S. A. R.
T: +852 3664 6888
F: +852 3664 6999