Contract
No. SS H504 Design and Construction of Chai
Wan Government Complex and Vehicle Depot 4th Monthly EM&A Report Yau Lee Construction Co, Ltd |
Document control record
Document prepared by:
Unit 1608, 16/F, Tower B, Manulife Financial Centre,
223 – 231 Wai Yip Street, Kwun Tong, Kowloon
Hong Kong S. A. R.
|
T |
+852 3664 6888 |
A person using
a) Using the documents or data in electronic
form without requesting and checking them for accuracy against the original
hard copy version.
b)
Using
the documents or data for any purpose not agreed to in writing by
|
Document control |
||||||
|
Report
title |
Fourth Monthly EM&A Report |
|||||
|
Document
ID |
MMR |
Project
number |
P520574 |
|||
|
File
path |
520574-0000-PLN-NM-0005 [0] |
|||||
|
Client |
|
|||||
|
Client
contact |
|
Client
reference |
|
|||
|
Rev |
Date |
Revision
details/status |
Author |
Reviewer |
Verifier
|
Approver |
|
0 |
|
Submitted to IEC |
Various |
K.Chau |
|
FL |
|
1 |
10 March 2022 |
Submitted to IEC |
Various |
K.Chau |
|
FL |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Current
revision |
|
|||||
|
Approval |
|||
|
Reviewer’s signature |
|
Approver’s signature |
|
|
Name |
Keith Chau |
Name |
Fredrick
Leong |
|
Title |
Principal Consultant, Environmental |
Title |
Executive Director, Environment & Planning - Greater China |
All
rights reserved | The information/data furnished in our document is
confidential and competitive information proprietary to Aurecon or its
subcontractors, the release of which would harm the competitive position
of Aurecon or its sub-contractors/consultants. This information/data shall
not be reproduced, stored in a retrieval system, transmitted in any form
or by any means, used or disclosed in whole or in part, for any purpose
other than to evaluate and adjudicate this document. If Aurecon is
shortlisted or a contract is awarded to Aurecon as a result of this
solicitation, or in connection with the submission of such
information/data, the right (and the extent thereof) to reproduce, store,
transmit, use or disclose this information/data must, by agreement, be
included in such contract.
Contents
3 Environmental Monitoring Requirements
4 Implementation Status on Environmental Mitigation
Measures
6 Environmental Site Inspection
7 Environmental Non-conformance
9 Review of EM&A Data and EIA Predictions
Appendix
|
Appendix 1 |
|
|
Appendix 2 |
|
|
Appendix 3 |
|
|
Appendix 4 |
|
|
Appendix 5 |
|
|
Appendix 6 |
|
|
Appendix 7 |
|
|
Appendix 8 |
|
|
Appendix 9 |
|
|
Appendix 10 |
Aurecon Hong Kong Limited (Aurecon) was commissioned by the Yau Lee Construction Co, Ltd (Yau Lee) to undertake the role of Environmental Team (ET) for carrying out the environmental monitoring and audit (EM&A) works for the “Contract No. SS H504 Design and Construction of Chai Wan Government Complex and Vehicle Depot (The Project).
An Environmental Permit (EP) No. EP-505/2015 was issued by the Environmental Protection Department (EPD) on 17 December 2015 for the construction of this project based on the Environmental Impact Assessment (EIA) Report (Register No: AEIAR-191/2015) approved by the EPD. The latest EP No. EP-505/2015/A was subsequently issued by the EPD on 8 November 2019 based on the documents (including an Environmental Review Report (ERR)) for the application of Variation of Environmental Permit.
The construction phase and EM&A programme of the Project commenced on 25 November 2021.
This 4th Monthly EM&A Report presents the EM&A works conducted from 1 February 2022 to 28 February 2022 in accordance with the EM&A Manual.
Summary of Construction
Works undertaken during Report Period
The major construction works undertaken during the reporting period include:
|
-
Pre-drilling work. (Zone A
& Zone B) |
|
-
Piling
work |
|
-
Tree
protection works |
Environmental Monitoring
and Audit Progress
A summary of the monitoring activities in this reporting period is listed below:
|
-
Construction Noise Monitoring
during normal weekdays at each monitoring station |
4 times |
|
-
Joint
Environmental Site Inspection |
2 times |
Nosie
4 sets of 30-minute construction noise measurement were carried out at each monitoring stations during normal weekdays of the reporting period. No exceedance of Action and Limit Levels of construction noise was recorded during the reporting period.
According
to the email notification received from Chai Wan THEi
Campus on 12 February 2022, due to current COVID-19 development, the monitoring
location at NM3 (Rooftop of Chai Wan THEi Campus) is
temporary inaccessible. The noise monitoring at NM3 has been temporary
relocated to the adjusted location from 12 February 2022 until further notice
from THEi.
Environmental Site
Inspection
Joint environmental site inspections were carried out on 07 and 24 February 2022. The joint environmental site inspection was carried out by the representatives of the Engineer's Representative (ER), the Contractor, IEC and the ET on 7 February 2022. The Contractor has generally implemented the mitigation measures as recommended. Due to COVID-19 preventative measures on site, the weekly site inspection on 17 Feb 2022 was cancelled. The arrangement has been notified to ER and IEC with no adverse comment received.
Environmental
Exceedance/Non-conformance/Compliant/Summons and Prosecution
No exceedance of the Action and Limit Levels of construction noise was recorded at designated monitoring stations during the reporting period.
No non-compliance event was recorded during the reporting period.
No environmental complaint and summons/prosecutions was received in this reporting period.
Future Key
Issues
Works to be undertaken in the next month include:
|
-
Tree protection works |
|
-
Pre-drilling
works. (Zone A & Zone B) |
|
-
Piling
works. |
|
-
Sheet
pile installation. |
|
-
ELS
works. |
|
-
Off-site
mock up construction. |
Potential environmental impacts arising from the above construction activities are mainly associated with dust, construction noise, site runoff and waste management.
Project site
|
Construction Activities Undertaken |
|
- Pre-drilling work. (Zone A & Zone B) |
|
- Pilling work. |
|
- Tree protection works |
|
Permit / Licenses / Notifiation |
Reference |
Validity Period |
Remark |
|
Environmental Permit (EP) |
EP-505/2015/A |
Throughout the Contract |
Permit granted on 8 November 2019 |
|
Notification of Construction Works as required
under Air Pollution Control (Construction Dust) Regulation |
469716 |
Throughout the Contract |
Approved on 21 July 2021 |
|
Registration of Waste Producer under Waste
Disposal Ordinance |
7041313 |
Throughout the Contract |
Approved on 13 August 2021 |
|
Registration as Chemical Waste Producer |
5213-163-Y2782-01 |
Throughout the Contract |
Approved on 24 August 2021 |
|
Construction Noise Permit |
GW-RS0759-21 |
15 October 2021 -14 April 2022 |
Approved on 4 October 2021 |
|
Effluent Discharge License under Water Pollution
Control Ordinance |
WT00038924-2021 |
30 September 2026 |
Approved on 9 December 2021 |
|
Proposed Noise Monitoring Location |
Remark |
|
|
NM1 |
Ground Floor at Heng Fa Chuen
Block 50 |
- |
|
NM2a |
Lamp Post no. 47447 at Sheung Mau Street |
* |
|
NM3 |
Rooftop of THEi Campus |
* |
|
Remark:
* - |
Hong
Kong Institute of Vocational Education (Chai Wan) - Academic Block (NM2) is
the noise monitoring stations for the construction phase EM&A programme
as identified in the approved EM&A Manual for the Project. The access to
NM2 and Knight Court (as a VTC Senior Quarters and NSR3 in approved EIA) were
denied. A search for alternative noise
monitoring locations along Shing Tai Road and Sheung Mau Street was carried
out during the site visit on 4 October 2021. Lamp
Post no. 47447 at Sheung Mau Street (NM2a), which
is located between project site and original noise monitoring location, Hong
Kong Institute of Vocational Education (Chai Wan) - Academic Block (NM2), is
found suitable and available to be an alternative noise monitoring location
for NM2. Also, NM2a, which has a direct line of
sight towards project site (where construction works will be carried out and
likely to have noise impacts), is located closer to project site than NM2 and
thus considered as a representative noise monitoring location. Monitoring
position at NM2a is proposed at 2m
above ground due to security concerns and minimize the road traffic noise
contribution. Noise measurement at NM2a will be
considered as free-field and a correction of +3dB(A)
would be made to the noise monitoring results. The alternative location of NM2a, were therefore proposed and agreed by the
Independent Environmental Checker (IEC). Due to
the adjustment of the location of AM2 to AM2a, the
measured noise levels at AM2a would represent the noise
levels at AM2. According
to the email notification received from Chai Wan THEi
Campus on 12 February 2022, due to current COVID-19 development, the
monitoring location at NM3 (Rooftop of Chai Wan THEi
Campus) is temporary inaccessible. The noise monitoring at NM3 has been
temporary relocated to the adjusted location named NM3a
from 12 February 2022 until further notice
from THEi. The location of NM3a
is shown in Figure 3-1. Due
to the adjustment of the location of NM3a to NM3, the
measured noise level at AM3a would represent the
noise levels at NM3. |
|
NM3a
|
Time Period |
Parameters |
|
Daytime on
normal weekdays (0700-1900 hrs) |
Leq(30 mins), L10(5
mins) and L90(5 mins) |
|
Evening time
on all days (1900-2300 hrs) and Holidays (including Sundays) during daytime
and evening (0700-2300 hrs) |
Leq(5 mins), L10(5
mins) and L90(5 mins) |
|
All days
during the night-time (2300-0700 hrs of the next
day) |
Leq(5 mins) L10(5
mins) and L90(5 mins) |
|
Monitoring Station |
Monitoring Equipment (Sound Level Meter and Calibrator) |
|
NM1 |
Sound
Level Meter: Rion NL 52(s/n:00643040) and (s/n:01010406) Calibrator:
Larson Davis Cal 200(s/n: 16878) |
|
NM2a |
|
| NM3 |
|
Monitoring Station |
Action Level |
Limit Level |
|
|
Nosfff Noise Criteria,Leq(30mins), dB(A) |
Remark |
||
|
NM1 |
When one
documented complaint is
received |
75 |
Applicable during 0700 – 1900 hours, Monday to Saturday |
|
NM2a |
70 65 (during
examination) |
||
| NM3 |
70 65 (during
examination) |
||
• NM1: Road traffic noise and railway noise.
• NM2a: Road traffic noise and Yau Lee Site.
• NM3: Road Traffic Noise. Minor noise from Cargo Handling Area.
·
When Measured noise level (Leq
30mins) > Baseline noise level (Leq30), Construction noise level is calculated
·
Construction noise level = Measured noise level (Leq 30 mins) – Baseline noise level
·
If Measured noise level (Leq
30mins) < Baseline noise level, Corrected noise
level = Measured noise level
07 February 2022
• Chemicals were observed without drip tray. Drip trays shall be provided for the chemical containers.
• Oil stain was observed underneath the generator. Oil stain shall be disposed of as chemical waste.
• The generator was observed without NRMM label. Proper NRMM label shall be affixed on the generator.
• Cement was not covered entirely by impervious sheeting. Cement bags shall be covered with impervious sheet.
• Muddy stockpile is observed next to vehicle entrance. Muddy stockpile next to the vehicle entrance shall be removed to prevent muddy washout site entrance.
24 February 2022
• The drip tray was full. The Contractor shall clean the drip tray regularly.
• The color of NRMM label was inaccurate. The Contractor was reminded to replace the NRMM labels.
- Tree protection works
- Pre-drilling works for pilling works. (Zone A & Zone B)
- Piling works
- Sheet pile installation.
- ELS work.
- Off site mock up construction.
|
Monitoring Station |
EIA Predicted Construction Noise Levels,
dB(A) |
Baseline Noise Levels, dB(A) |
Noise Monitoring Results, dB(A) |
|
|
|
Leq(30mins),
Average |
Range |
||
|
NM1 |
62 |
65.1 |
64.8 |
64-67 |
|
NM2a |
69 |
73.4 |
73.8 (65.3*) |
73-75 (51-73*) |
|
NM3 |
66 |
69.8 |
67.3 |
67-68 |
Note: *The measured noise
levels exceeded the noise level of 70dB(A) and they
were higher than the baseline level of 73.4 dB(A) for NM2a. Therefore, baseline corrections were carried
out and the corrected noise levels which solely represent the noise levels of Construction
works are lower than the noise criteria. As such the EAP was not triggered. Details are mentioned in Section 5.1.3 and
summarised in Appendix 7.
Appendix 1
Appendix 2
Appendix 3
Appendix 4
Appendix 5
Appendix 6
Appendix 7
Appendix 8
Appendix 9
Appendix 10
Prepared by:
Aurecon Hong Kong
Limited
Unit 1608, 16/F, Tower
B, Manulife Financial Centre,
223 – 231 Wai Yip
Street, Kwun Tong,
Kowloon Hong Kong S.
A. R.
T: +852 3664 6888
F: +852 3664 6999