|
Contract
No. SS H504 Design and Construction of Chai Wan Government Complex and
Vehicle Depot 41st Monthly
EM&A Report Yau Lee Construction Co, Ltd 2025-04-09 |
Document control record
Document prepared by:
Unit 1608, 16/F, Tower B, Manulife Financial Centre,
223 – 231 Wai Yip Street, Kwun Tong, Kowloon
Hong Kong S. A. R.
|
T |
+852 3664 6888 |
A person using
a) Using the documents or data in electronic
form without requesting and checking them for accuracy against the original
hard copy version.
b)
Using
the documents or data for any purpose not agreed to in writing by
|
Document control |
||||||
|
Report
title |
41st Monthly EM&A Report |
|||||
|
Document
ID |
MMR |
Project
number |
P520574 |
|||
|
File
path |
520574-0000-PLN-NM-00043 [0] |
|||||
|
Client |
|
|||||
|
Client
contact |
|
Client
reference |
|
|||
|
Rev |
Date |
Revision
details/status |
Author |
Reviewer |
Verifier
|
Approver |
|
0 |
|
Submitted to IEC |
Various |
K.Chau |
|
FL |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Current
revision |
|
|||||
|
Approval |
|||
|
Reviewer’s signature |
|
Approver’s signature |
|
|
Name |
Keith Chau |
Name |
Fredrick
Leong |
|
Title |
Associate, Environmental |
Title |
Environmental Team Leader |
All
rights reserved | The information/data furnished in our document is
confidential and competitive information proprietary to Aurecon or its
subcontractors, the release of which would harm the competitive position
of Aurecon or its sub-contractors/consultants. This information/data
shall not be reproduced, stored in a retrieval system, transmitted in any
form or by any means, used or disclosed in whole or in part, for any
purpose other than to evaluate and adjudicate this document. If Aurecon
is shortlisted or a contract is awarded to Aurecon as a result of this
solicitation, or in connection with the submission of such
information/data, the right (and the extent thereof) to reproduce, store,
transmit, use or disclose this information/data must, by agreement, be
included in such contract.
All
rights reserved | The information/data furnished in our document is
confidential and competitive information proprietary to Aurecon or its
subcontractors, the release of which would harm the competitive position
of Aurecon or its sub-contractors/consultants. This information/data shall
not be reproduced, stored in a retrieval system, transmitted in any form
or by any means, used or disclosed in whole or in part, for any purpose
other than to evaluate and adjudicate this document. If Aurecon is
shortlisted or a contract is awarded to Aurecon as a result of this
solicitation, or in connection with the submission of such
information/data, the right (and the extent thereof) to reproduce, store,
transmit, use or disclose this information/data must, by agreement, be
included in such contract.
Contents
3 Environmental Monitoring Requirements
4 Implementation Status on Environmental Mitigation
Measures
6 Environmental Site Inspection
7 Environmental Non-conformance
9 Review of EM&A Data and EIA Predictions
Appendix
|
Appendix 1 |
|
|
Appendix 2 |
|
|
Appendix 3 |
|
|
Appendix 4 |
|
|
Appendix 5 |
|
|
Appendix 6 |
|
|
Appendix 7 |
|
|
Appendix 8 |
|
|
Appendix 9 |
|
|
Appendix 10 |
|
|
Appendix 11 |
Notification of Environmental Quality Limits Exceedance |
|
Appendix
12 |
Cumulative Complaint / Enquiry Log,
Summaries of Complaints and Enquiries |
Aurecon Hong Kong Limited (Aurecon) was commissioned by the Yau Lee Construction Co, Ltd (Yau Lee) to undertake the role of Environmental Team (ET) for carrying out the environmental monitoring and audit (EM&A) works for the “Contract No. SS H504 Design and Construction of Chai Wan Government Complex and Vehicle Depot (The Project).
An Environmental Permit (EP) No. EP-505/2015 was issued by the Environmental Protection Department (EPD) on 17 December 2015 for the construction of this project based on the Environmental Impact Assessment (EIA) Report (Register No: AEIAR-191/2015) approved by the EPD. The latest EP No. EP-505/2015/A was subsequently issued by the EPD on 8 November 2019 based on the documents (including an Environmental Review Report (ERR)) for the application of Variation of Environmental Permit.
The construction phase and EM&A programme of the Project commenced on 25 November 2021.
This 41st Monthly EM&A Report presents the EM&A works conducted from 01 March 2025 to 31 March 2025 in accordance with the EM&A Manual.
Summary of Construction
Works undertaken during Report Period
The major construction works undertaken during the reporting period include:
|
- Rebar fixing |
|
- Formwork erection |
|
- Concreting works |
|
- Installation of MiC and
precast elements |
|
- Finishing works and BS installation works |
Environmental Monitoring
and Audit Progress
A summary of the monitoring activities in this reporting period is listed below:
|
-
Construction Noise Monitoring
during normal weekdays at each monitoring station |
4 times |
|
-
Joint
Environmental Site Inspection |
4 times |
Noise
4 sets of 30-minute construction noise measurement were carried out at each monitoring stations during normal weekdays of the reporting period. No exceedance of Action and Limit Levels of construction noise was recorded during the reporting period.
Environmental
Site Inspection
Joint environmental site inspections were carried out on 07, 13, 20 and 27 March 2025. The joint environmental site inspection was carried out by the representatives of the Engineer's Representative (ER), the Contractor, IEC and the ET on 07 March 2025. The Contractor has generally implemented the mitigation measures as recommended.
Environmental
Exceedance/Non-conformance/Compliant/Summons and Prosecution
No exceedance of the Action and Limit Levels of construction noise was recorded at designated monitoring stations during the reporting period.
No non-compliance event was recorded during the reporting period.
No environmental complaint and no summons/prosecutions were received in this reporting period.
EPD conducted general site inspection on 11 March 2025. No special findings were identified during the inspection.
Future
Key Issues
Works to be undertaken in the next month include:
|
-
Superstructure construction (L8 – UR/F) |
|
-
Rebar fixing |
|
-
Formwork erection |
|
-
Concreting works |
|
-
Installation of Mic and precast
elements |
|
-
Finishing works and BS installation works |
Potential environmental impacts arising from the above construction activities are mainly associated with dust, construction noise, site runoff and waste management.
Project site
|
Construction Activities Undertaken |
|
-
Rebar
fixing |
|
-
Formwork
erection |
|
-
Concreting
works |
|
-
Installation
of MiC and precast elements |
|
-
Finishing works and BS
installation works |
|
Permit / Licenses / Notification |
Reference |
Validity Period |
Remark |
|
Environmental Permit (EP) |
EP-505/2015/A |
Throughout the Contract |
Permit granted on 8 November 2019 |
|
Notification of Construction Works as required
under Air Pollution Control (Construction Dust) Regulation |
469716 |
Throughout the Contract |
Approved on 21 July 2021 |
|
Registration of Waste Producer under Waste
Disposal Ordinance |
7041313 |
Throughout the Contract |
Approved on 13 August 2021 |
|
Registration as Chemical Waste Producer |
5213-163-Y2782-01 |
Throughout the Contract |
Approved on 24 August 2021 |
|
Effluent Discharge License under Water Pollution
Control Ordinance |
WT00038924-2021 |
30 September 2026 |
Approved on 9 December 2021 |
|
Proposed Noise Monitoring Location |
Remark |
|
|
NM1 |
Ground Floor at Heng Fa Chuen Block 50 |
- |
|
NM2b |
Pedestrian
road at Shing Tai Road |
* |
|
NM3 |
Rooftop of THEi Campus |
- |
|
Remark: * - |
Hong
Kong Institute of Vocational Education (Chai Wan) - Academic Block (NM2) is
the noise monitoring stations for the construction phase EM&A programme
as identified in the approved EM&A Manual for the Project. The access to
NM2 and Knight Court (as a VTC Senior Quarters and NSR3 in approved EIA) were
denied. A search for alternative
noise monitoring locations along Shing Tai Road and Sheung Mau Street was
carried out during the site visit on 4 October 2021. Lamp
Post no. 47447 at Sheung Mau Street (NM2a), which is located between project
site and original noise monitoring location, Hong Kong Institute of
Vocational Education (Chai Wan) - Academic Block (NM2), is found suitable and
available to be an alternative noise monitoring location for NM2. Also, NM2a,
which has a direct line of sight towards project site (where construction
works will be carried out and likely to have noise impacts), is located
closer to project site than NM2 and thus considered as a representative noise
monitoring location. Monitoring position at NM2a is proposed at 2m above
ground due to security concerns and minimize the road traffic noise
contribution. Noise measurement at NM2a will be considered as free-field and
a correction of +3dB(A) would be made to the noise monitoring results. The alternative location of NM2a, were
therefore proposed and agreed by the Independent Environmental Checker (IEC).
Due to
the adjustment of the location of NM2 to NM2a, the measured noise levels at NM2a
would represent the noise levels at NM2. To
respond to the comment raised by EPD on monitoring location of NM2a by email
dated 23 May 2022 and site meeting on 6 June 2022, the monitoring location of
NM2a was adjusted to the pedestrian road at Shing Tai Road (NM2b) which is located
between project site and original noise monitoring location, Hong Kong
Institute of Vocational Education (Chai Wan) - Academic Block (NM2). Compared
with NM2a, NM2b is far away from the traffic light and therefore should be
able to minimise the traffic noise issue. This arrangement was started from 28
June 2022 and has been agreed by the Independent Environmental Checker (IEC).
Noise measurement at NM2b will be considered as free-field and a correction
of +3dB(A) would be made to the noise monitoring results. Due to
the adjustment of the location of NM2a to NM2b, the measured noise level at
NM2b would represent the noise levels at NM2. |
|
|
Time Period |
Parameters |
|
Daytime on
normal weekdays (0700-1900 hrs) |
Leq(30 mins), L10(5 mins) and L90(5
mins) |
|
Evening time
on all days (1900-2300 hrs) and Holidays (including Sundays) during daytime
and evening (0700-2300 hrs) |
Leq(5 mins), L10(5 mins) and L90(5
mins) |
|
All days
during the night-time (2300-0700 hrs of the next
day) |
Leq(5 mins) L10(5 mins) and L90(5
mins) |
|
Monitoring Station |
Monitoring Equipment (Sound Level Meter and Calibrator) |
|
NM1 |
Sound
Level Meter: Rion NL 52(s/n:00643039)
Calibrator:
Larson Davis Cal 200(s/n: 10227) |
|
NM2b |
|
| NM3 |
|
Monitoring Station |
Action Level |
Limit Level |
|
|
Noise Criteria, Leq(30mins), dB(A) |
Remark |
||
|
NM1 |
When one
documented complaint is received |
75 |
Applicable during 0700 – 1900 hours, Monday to Saturday |
|
NM2b |
70 65 (during
examination) |
||
| NM3 |
70 65 (during
examination) |
||
I.
The timing and sequence of construction activities were carefully
arranged.
II.
QPME were used to reduce the excessive noise impact.
III.
Good site practices were implemented to reduce noise impact of the site
activities. The practices are listed as below:
-
Use only well-maintained and regularly-serviced plant during the works;
-
Turn off or throttle down the plant in intermittent use to a minimum;
-
Orient the plant known to emit noise strongly in one direction to face
away from the NSRs;
-
Use silencers, mufflers and enclosures for plant where possible and
maintain properly throughout the works;
-
Site fixed plant as far away from NSRs as possible; and
-
Use stockpiles of excavated materials and other structures such as site
buildings effectively to screen noise from the works.
IV.
Movable noise barrier/acoustic sheet barriers as noise shield were adopted
as far as practicable following the Construction Noise Management Plan (CNMP).
• NM1: Railway noise, traffic noise and Yau Lee Site.
• NM2b: Road traffic noise and Yau Lee Site.
• NM3: Cargo Handling Area and Yau Lee Site.
5.1.4
The methodology
is shown as below:
·
When Measured noise level (Leq
30mins) > Baseline noise level (Leq30), Construction noise level is
calculated
·
Construction noise level = Measured noise level (Leq 30 mins) – Baseline noise level
·
If Measured noise level (Leq
30mins) < Baseline noise level, Corrected noise level = Measured noise level
6.1.1
Joint environmental site inspection was conducted in the reporting period
on 07, 13, 20 and 27 March 2025. The joint environmental
site inspection was carried out by the representatives of the Engineer's
Representative (ER), the Contractor, IEC and the ET on 07
March 2025. The joint environmental site inspection record is shown in Appendix 9. There was no noncompliance recorded during the site inspections.
07
March 2025
• Dry PFA material was observed on L4. The
Contractor has been recommended that dry PFA material should be stored properly
and covered by impervious sheet to avoid dust dispersion.
• The accumulated C&D waste was observed on L6. The Contractor has been recommended to dispose of waste more frequently to avoid waste accumulation.
13 March 2025
• Surface runoff with silt and grit was observed on G/F. The Contractor has been recommended to remove silt and grit in the drainage channel to ensure the efficiency of the drainage channel and direct the surface runoff into the silt removal facility.
20 March 2025
• Dry PFA materials were observed on L5. The Contractor has been recommended to store dry PFA materials properly and cover them by
• Stockpiling of dusty material without impervious sheet was observed on G/F. The Contractor has been advised that dusty materials should be covered by impervious sheeting or sprayed with water and removed or backfilled or reinstated within 24 hours of the excavation or unloading.
Table 7-1 Cumulative Statistics on Environmental Complaints
|
Reporting
Period |
Environmental Aspects |
|||||
|
Air Quality |
Noise |
Water Quality |
Waste |
Ecology |
||
|
Mar 2025 |
Complaint
Date |
- |
- |
- |
- |
- |
|
No. of Complaint |
0 |
0 |
0 |
0 |
0 |
|
|
Reporting Period Total |
0 |
0 |
0 |
0 |
0 |
|
|
Accumulate of project |
0 |
1* |
0 |
0 |
0 |
|
Remarks:
1. * Equal to non-project
related after the investigation.
- Superstructure
construction (L8-UR/F)
- Rebar
fixing
- Formwork
erection
- Concreting works
- Installation of MiC
and Precast Elements
- Finishing works and
BS installation works
|
Monitoring Station |
EIA Predicted Construction Noise Levels,
dB(A) |
Baseline Noise Levels, dB(A) |
Noise Monitoring Results, dB(A) |
|
|
|
Leq(30mins), Average |
Range |
||
|
NM1 |
62 |
65.1 |
63.3 |
63-64 |
|
NM2b |
69 |
73.4 |
71.2* |
69-73* |
|
NM3 |
66 |
69.8 |
65.8 |
65-66 |
Note: * The measured noise levels exceeded the limit noise level of
70 dB for NM2b, but
they were lower than the baseline level for NM2b. Therefore, they were not
considered as an exceedance of limit level. As such the EAP was not triggered.
Appendix 1
Appendix 2
Appendix 3
Appendix 4
Appendix 5
Appendix 6
Appendix 7
Appendix 8
Appendix 9
Appendix 10
Appendix 11
There was no Notification of Environmental Quality Limits Exceedance
in the reporting month.
Appendix 12
Prepared by:
Aurecon Hong Kong
Limited
Unit 1608, 16/F, Tower
B, Manulife Financial Centre,
223 – 231 Wai Yip
Street, Kwun Tong,
Kowloon Hong Kong S.
A. R.
T: +852 3664 6888
F: +852 3664 6999