Contract
No. SS H504 Design and Construction of Chai Wan Government Complex and
Vehicle Depot 51st Monthly
EM&A Report Yau Lee Construction Co, Ltd 2026-02-27 |
Document control record
Document prepared by:
Unit 1608, 16/F, Tower B, Manulife Financial Centre,
223 – 231 Wai Yip Street, Kwun Tong, Kowloon
Hong Kong S. A. R.
|
T |
+852 3664 6888 |
A person using
a) Using the documents or data in electronic
form without requesting and checking them for accuracy against the original
hard copy version.
b)
Using
the documents or data for any purpose not agreed to in writing by
|
Document control |
||||||
|
Report
title |
51st Monthly
EM&A Report |
|||||
|
Document
ID |
MMR |
Project
number |
P520574 |
|||
|
File
path |
520574-0000-PLN-NM-00045 [0] |
|||||
|
Client |
|
|||||
|
Client
contact |
|
Client
reference |
|
|||
|
Rev |
Date |
Revision
details/status |
Author |
Reviewer |
Verifier
|
Approver |
|
0 |
|
Submitted to IEC |
Various |
K.Chau |
|
FL |
|
1 |
09 February 2026 |
Submitted to IEC |
Various |
K.Chau |
|
FL |
|
2 |
27 February 2026 |
Submitted to IEC |
Various |
K.Chau |
|
FL |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Current
revision |
|
|||||
|
Approval |
|||
|
Reviewer’s signature |
|
Approver’s signature |
|
|
Name |
Keith Chau |
Name |
Fredrick
Leong |
|
Title |
Associate,
Environmental |
Title |
Environmental
Team Leader |
Contents
3 Environmental Monitoring Requirements
4 Implementation Status on Environmental Mitigation
Measures
6 Environmental Site Inspection
7 Environmental Non-conformance
9 Review of EM&A Data and EIA Predictions
Appendix
|
Appendix 1 |
|
|
Appendix 2 |
|
|
Appendix 3 |
|
|
Appendix 4 |
|
|
Appendix 5 |
|
|
Appendix 6 |
|
|
Appendix 7 |
|
|
Appendix 8 |
|
|
Appendix 9 |
|
|
Appendix 10 |
Notification
of Environmental Quality Limits Exceedance |
|
Appendix 11 |
Cumulative Complaint / Enquiry Log,
Summaries of Complaints and Enquiries |
Aurecon Hong Kong Limited (Aurecon) was commissioned by the Yau Lee Construction Co, Ltd (Yau Lee) to undertake the role of Environmental Team (ET) for carrying out the environmental monitoring and audit (EM&A) works for the “Contract No. SS H504 Design and Construction of Chai Wan Government Complex and Vehicle Depot (The Project).
An Environmental Permit (EP) No. EP-505/2015 was issued by the Environmental Protection Department (EPD) on 17 December 2015 for the construction of this project based on the Environmental Impact Assessment (EIA) Report (Register No: AEIAR-191/2015) approved by the EPD. The latest EP No. EP-505/2015/A was subsequently issued by the EPD on 8 November 2019 based on the documents (including an Environmental Review Report (ERR)) for the application of Variation of Environmental Permit.
The construction phase and EM&A programme of the Project commenced on 25 November 2021.
This
51st Monthly EM&A Report presents
the EM&A works conducted from 01 January
2026 to 18 January 2026 in
accordance with the EM&A Manual. The termination of the EM&A Programme
(Construction Phase) was approved by the EPD on 13 January 2026. And the EM&A Programme
(Construction Phase), including noise monitoring and site inspections, was
terminated since 19 January 2026.
Summary of Construction
Works undertaken during Report Period
The
major construction works undertaken during the reporting period include:
|
- Construction works of the project have been completed |
Environmental Monitoring
and Audit Progress
A summary of the monitoring activities in this reporting period is listed below:
|
-
Construction Noise Monitoring
during normal weekdays at each monitoring station |
2 times |
|
-
Joint
Environmental Site Inspection |
3 times |
Noise
2 sets of 30-minute construction noise measurement were carried out at each monitoring stations during normal weekdays of the reporting period. No exceedance of Action and Limit Levels of construction noise was recorded during the reporting period.
Environmental
Site Inspection
Joint environmental site inspections were carried out on 02, 09 and 16 January 2026. The joint environmental site inspection was carried out by the representatives of the Engineer's Representative (ER), the Contractor, IEC and the ET on 16 January 2026. The Contractor has generally implemented the mitigation measures as recommended.
Environmental
Exceedance/Non-conformance/Compliant/Summons and Prosecution
No exceedance of the Action and Limit Levels of construction noise was recorded at designated monitoring stations during the reporting period.
No non-compliance event was recorded during the reporting period.
No environmental complaint and no summons/prosecutions were received in this reporting period.
EPD general site inspection was not conducted in the reporting month. No special findings were identified.
Future
Key Issues
The
construction works for the project have been completed; therefore, no
potential environmental impact will be arising from the site.
The termination of the EM&A Programme (Construction Phase) was approved by
the EPD on 13 January 2026. And the EM&A Programme (Construction Phase), including noise monitoring and
site inspections, was terminated since 19 January 2026.
|
Construction Activities
Undertaken |
|
-
Construction works of the
project have been completed |
|
Permit / Licenses / Notification |
Reference |
Validity Period |
Remark |
|
Environmental Permit (EP) |
EP-505/2015/A |
Throughout the Contract |
Permit granted on 8 November 2019 |
|
Notification of Construction Works as required
under Air Pollution Control (Construction Dust) Regulation |
469716 |
Throughout the Contract |
Approved on 21 July 2021 |
|
Registration of Waste Producer under Waste
Disposal Ordinance |
7041313 |
Throughout the Contract |
Approved on 13 August 2021 |
|
Registration as Chemical Waste Producer |
5213-163-Y2782-01 |
Throughout the Contract |
Approved on 24 August 2021 |
|
Effluent Discharge License under Water Pollution
Control Ordinance |
WT00038924-2021 |
30 September 2026 |
Approved on 9 December 2021 |
|
Proposed Noise Monitoring Location |
Remark |
|
|
NM1 |
Ground Floor at Heng Fa Chuen
Block 50 |
- |
|
NM2b |
Pedestrian
road at Shing Tai Road |
* |
|
NM3 |
Rooftop of THEi Campus |
- |
|
Remark: * - |
Hong
Kong Institute of Vocational Education (Chai Wan) - Academic Block (NM2) is
the noise monitoring stations for the construction phase EM&A programme
as identified in the approved EM&A Manual for the Project. The access to
NM2 and Knight Court (as a VTC Senior Quarters and NSR3 in approved EIA) were
denied. A search for alternative
noise monitoring locations along Shing Tai Road and Sheung Mau Street was
carried out during the site visit on 4 October 2021. Lamp
Post no. 47447 at Sheung Mau Street (NM2a), which is located between project
site and original noise monitoring location, Hong Kong Institute of
Vocational Education (Chai Wan) - Academic Block (NM2), is found suitable and
available to be an alternative noise monitoring location for NM2. Also, NM2a,
which has a direct line of sight towards project site (where construction
works will be carried out and likely to have noise impacts), is located
closer to project site than NM2 and thus considered as a representative noise
monitoring location. Monitoring position at NM2a is proposed at 2m above
ground due to security concerns and minimize the road traffic noise
contribution. Noise measurement at NM2a will be considered as free-field and
a correction of +3dB(A) would be made to the noise monitoring results. The alternative location of NM2a, were
therefore proposed and agreed by the Independent Environmental Checker (IEC).
Due to
the adjustment of the location of NM2 to NM2a, the measured noise levels at NM2a
would represent the noise levels at NM2. To
respond to the comment raised by EPD on monitoring location of NM2a by email
dated 23 May 2022 and site meeting on 6 June 2022, the monitoring location of
NM2a was adjusted to the pedestrian road at Shing Tai Road (NM2b) which is located
between project site and original noise monitoring location, Hong Kong
Institute of Vocational Education (Chai Wan) - Academic Block (NM2). Compared
with NM2a, NM2b is far away from the traffic light and therefore should be
able to minimise the traffic noise issue. This arrangement was started from 28
June 2022 and has been agreed by the Independent Environmental Checker (IEC).
Noise measurement at NM2b will be considered as free-field and a correction
of +3dB(A) would be made to the noise monitoring results. Due to
the adjustment of the location of NM2a to NM2b, the measured noise level at
NM2b would represent the noise levels at NM2. |
|
|
Time Period |
Parameters |
|
Daytime on
normal weekdays (0700-1900 hrs) |
Leq(30 mins), L10(5 mins) and L90(5
mins) |
|
Evening time
on all days (1900-2300 hrs) and Holidays (including Sundays) during daytime
and evening (0700-2300 hrs) |
Leq(5 mins), L10(5 mins) and L90(5
mins) |
|
All days
during the night-time (2300-0700 hrs of the next
day) |
Leq(5 mins) L10(5 mins) and L90(5
mins) |
|
Monitoring Station |
Monitoring Equipment (Sound Level Meter and Calibrator) |
|
NM1 |
Sound
Level Meter: Rion NL 52(s/n:
00331805) Calibrator:
Larson Davis Cal 200(s/n: 10227) |
|
NM2b |
|
| NM3 |
|
Monitoring Station |
Action Level |
Limit Level |
|
|
Noise Criteria, Leq(30mins), dB(A) |
Remark |
||
|
NM1 |
When one documented complaint is received |
75 |
Applicable during 0700 – 1900 hours, Monday to Saturday |
|
NM2b |
70 65 (during
examination) |
||
| NM3 |
70 65 (during
examination) |
||
I.
The timing and sequence of construction activities were carefully
arranged.
II.
QPME were used to reduce the excessive noise impact.
III.
Good site practices were implemented to reduce noise impact of the site
activities. The practices are listed as below:
- Use only well-maintained and
regularly-serviced plant during the works;
- Turn off or throttle down the
plant in intermittent use to a minimum;
- Orient the plant known to emit
noise strongly in one direction to face away from the NSRs;
- Use silencers, mufflers and
enclosures for plant where possible and maintain properly throughout the works;
- Site fixed plant as far away from
NSRs as possible; and
- Use stockpiles of excavated
materials and other structures such as site buildings effectively to screen
noise from the works.
IV.
Movable noise barrier/acoustic sheet barriers as noise shield were adopted
as far as practicable following the Construction Noise Management Plan (CNMP).
|
• NM1: |
Railway noise, traffic noise, other construction site. |
|
• NM2b: |
Road traffic noise, other construction site. |
|
• NM3: |
Cargo Handling Area,
other construction site. |
5.1.4
The methodology
is shown as below:
·
When Measured noise level (Leq 30mins) >
Baseline noise level (Leq30), Construction noise level is calculated
·
Construction noise level = Measured noise level (Leq
30 mins) – Baseline noise level
·
If Measured noise level (Leq 30mins) <
Baseline noise level, Corrected noise level = Measured noise level
6.1.1
Joint environmental site inspections were conducted in the reporting
period on 02, 09, and 16 January 2026. The joint environmental
site inspection was carried out by the representatives of the Engineer's
Representative (ER), the Contractor, IEC and the ET on 16
January 2026. The joint environmental
site inspection record is shown in Appendix
9. There was no
noncompliance recorded during the site inspections.
02
January 2026
• Nil.
09 January 2026
• Nil.
16 January 2026
• Nil.
Table 7-1 Cumulative Statistics on Environmental Complaints
|
Reporting Period |
Environmental
Aspects |
|||||
|
Air Quality |
Noise |
Water Quality |
Waste |
Ecology |
||
|
January 2026 |
Complaint
Date |
- |
- |
- |
- |
- |
|
No. of Complaint |
0 |
0 |
0 |
0 |
0 |
|
|
Reporting Period Total |
0 |
0 |
0 |
0 |
0 |
|
|
Accumulate of
project |
0 |
1* |
0 |
0 |
0 |
|
Remarks:
1. * Equal to non-project
related after the investigation.
|
Monitoring Station |
EIA Predicted Construction Noise Levels,
dB(A) |
Baseline Noise Levels, dB(A) |
Noise Monitoring Results, dB(A) |
|
|
|
Leq(30mins), Average |
Range |
||
|
NM1 |
62 |
65.1 |
64.5 |
64 – 65 |
|
NM2b |
69 |
73.4 |
71 |
69 – 73 * |
|
NM3 |
66 |
69.8 |
64.5 |
64 – 65 |
Note:
* On 12 January 2026, the measured noise levels of NM2b exceeded the limit level
of 70dB(A). However, they were lower than the baseline level of 73.4 dB(A). Therefore, they are not considered as a limit level
exceedance. As such the EAP was not triggered.
10.1.1
For construction noise, no Action or Limit Level
exceedance was recorded at the monitoring stations during the reporting period.
Appendix 1
Appendix 2
Appendix 3
Appendix 4
Appendix 5
Appendix 6
Appendix 7
Appendix 8
Appendix 9
Appendix 10
There was no Notification of
Environmental Quality Limits Exceedance in the reporting month.
Appendix 11
Prepared by:
Aurecon Hong Kong Limited
Unit 1608, 16/F, Tower B, Manulife Financial Centre,
223 – 231 Wai Yip Street, Kwun Tong,
Kowloon Hong Kong S. A. R.
T: +852 3664 6888
F: +852 3664 6999